Post by downunderdave on Jul 19, 2016 19:25:30 GMT
Bit more work done today will do the front tomorrow:) not sure how high I should take the bricks tho before putting a flue on The oven will draw better and have less smoke out the front at startup if you taper the flue gallery like an upside down funnel to meet the flue pipe. It doesn't matter how tall it is although you don't want too much weight up there, also more thermal mass outside the oven proper acts as a heat sink drawing more heat away from the oven.
|
|
|
Post by tim1989 on Jul 19, 2016 19:41:53 GMT
Does this have to be done stright away or could I set bricks at a 45 from where I am now?
|
|
|
Post by downunderdave on Jul 19, 2016 21:31:22 GMT
Does this have to be done stright away or could I set bricks at a 45 from where I am now? Either will do. It's just that if the smoke has somewhere to collect before entering the flue pipe, you get less escaping from out the front. it is well worth the effort to do this, after all the reason you have a flue is to remove the smoke.
|
|
|
Post by tim1989 on Jul 20, 2016 10:52:36 GMT
Got some toys delivered today
|
|
|
Post by tim1989 on Jul 20, 2016 18:03:29 GMT
I'm leaving the chimney there now to I sort a ss flue to build to. Can anyone help with what size I need will 4inch do? And does it have to be a double skin or will single do :/ Not got work to Monday so I will being doing the insulation tomorrow:)
|
|
|
Post by downunderdave on Jul 20, 2016 20:30:59 GMT
I'm leaving the chimney there now to I sort a ss flue to build to. Can anyone help with what size I need will 4inch do? And does it have to be a double skin or will single do :/ Not got work to Monday so I will being doing the insulation tomorrow:) You need a 6" diam stainless flue for a 36" oven. Only need a double flue if it's penetrating a roof. Even then you can get away with only making it double from where it goes through the roof to the the top. The flue pipe should extend 2' past the.roof.
|
|
|
Post by tim1989 on Jul 23, 2016 14:34:17 GMT
How much insulation do people normally use? I have 7.5meters of ceramic wool from kilnlinings it's the 128kg 1inch thick one. I have gone over the hole done once and have 2meter left should I just use this to do the top again or should I buy more?
|
|
|
Post by tim1989 on Jul 23, 2016 16:51:22 GMT
I ordered 7 more meter better safe then sorry
|
|
|
Post by oblertone on Jul 24, 2016 11:01:30 GMT
Insulation is key, and once done is very difficult to re-do so your extra 7m won't go amiss. As per your previous post, use any extra on the top.
|
|
|